Nature
of Claimant’s Interest |
|
Particulars
of Claim |
Amount
of Damages Claimed |
|
|
Contractor for the repairs of the Sheffield & Tinsley Turnpike Road |
|
To amount paid for damages caused by the Flood from the bursting of the Bradfield Reservoir |
|
|
|
|
|
|
Manual Labour |
£47 |
3s |
7d |
|
|
|
Team Labour |
£13 |
12s |
|
|
|
|
450 Tons of dross washed out of depot @ 5/. |
£135 |
|
|
|
|
|
Stone Depot Wall rebuilding |
£5 |
18s |
6d |
|
|
|
35 Road Guards @ 14/. |
£24 |
10s |
|
|
|
|
Damage to the Road from Lady's Bridge to Washford Bridge |
£300 |
|
|
|
|
|
New Floor in the Wicker Weighing Machine House |
£3 |
|
|
|
|
|
Partial stoppage in Traffic by the loss in Tool |
£10 |
|
|
|
|
|
Damage to Stone in Stone Yard |
£1 |
|
|
|
|
|
William Hazlewood as per note |
£3 |
15s |
9d |
|
|
|
|
|
£543 |
19s |
10d |
|
|
Certificate Granted
6 June 1865 |
Assessed by Agreement incl costs at |
£500 |
|
|
|